MISO-J1575
70 MW generation in Marshall, MN · In queue since June 2020 · Proposed COD December 2025
70 MW
Capacity
1
Components
Wind
6y 4m
In Queue
IA Pending
IA Phase
Signed Aug 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 2m
IA → COD
1y 4m
Total Duration
4y 2m
Schedule
11 months past proposed COD
Study Phase
DPP-2020 West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 18–36 months
Proposed COD: 2025-12-01
MISO-J1575 is a proposed 70 MW wind generation project located in Marshall County, Minnesota. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Otter Tail Power Company identified as the interconnecting utility. No developer name is listed in the available queue data. The project proposes to interconnect at a point on the 115 kV transmission line running from Warsaw to Donaldson, which is owned by Otter Tail Power Company. It has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO queue on June 25, 2020, and holds an active status. It is being evaluated in the DPP-2020 West study phase of MISO's Definitive Planning Phase process. Its interconnection agreement status is listed as "IA Pending," with an associated date of August 15, 2024. The proposed commercial operation date for the project is December 1, 2025.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MN
County
Marshall
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
115 kV transmission line from Warsaw to Donaldson owned by Otter Tail Power Company
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTW.NCENT.ARR
- POI Substation
- Ames Transmission Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1575Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.