MISO-J1572
150 MW hybrid in Faribault, MN · In queue since June 2020 · Proposed COD October 2023
150 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Pending
IA Phase
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 4m
Schedule
37 months past proposed COD
Study Phase
DPP-2020 West
Interconnection request submitted to ISO/RTO
Done; post-GIA Not Started; GIA
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-15
MISO-J1572 is a proposed hybrid solar and battery storage development project in Faribault County, Minnesota, with a total capacity of 150 megawatts (MW). The project data lists a 150 MW solar component. A battery storage element is also listed, but no separate capacity is given for it. The project would connect to the Huntley to Blue Earth 161 kV transmission line, in the service territory of Northern States Power Company. No developer name is identified in the available data.
The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, which it entered on June 23, 2020. It remains active and is being evaluated in the DPP-2020 West study phase. It has requested Network Resource Interconnection Service (NRIS). Its interconnection agreement is listed as pending. The proposed commercial operation date was October 15, 2023, which has already passed while the project is still under study.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MN
County
Faribault
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Huntley to Blue Earth 161kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1572Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.