MISO-J1534
100 MW generation in Olmsted, MN · In queue since April 2025 · Proposed COD June 2023
100 MW
Capacity
1
Components
Solar
1y 6m
In Queue
IA Pending
IA Phase
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 6m
Schedule
41 months past proposed COD
Study Phase
DPP-2020 West
Interconnection request submitted to ISO/RTO
Done; post-GIA Not Started; GIA
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-01
MISO-J1534 is a proposed 100 MW solar generation project in Olmsted County, Minnesota. It is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with the Southern Minnesota Municipal Power Agency as the associated utility. The developer has not been publicly identified in the queue data. The project would connect to the grid at the Byron point of interconnection and has requested Network Resource Interconnection Service (NRIS).
The project holds active status in the MISO queue, with a recorded queue date of April 14, 2025. It is being evaluated in the DPP-2020 West study phase, and its interconnection agreement is pending. The queue data lists a proposed commercial operation date of June 1, 2023, which falls before the recorded queue entry date.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MN
County
Olmsted
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Byron
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Byron Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.