MISO-J1437
180 MW generation in Carroll, AR · In queue since April 2019 · Proposed COD April 2021
180 MW
Capacity
1
Components
Wind
7y 6m
In Queue
Construction
IA Phase
Signed Dec 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 8m
Total Duration
2y 8m
Schedule
67 months past proposed COD
Study Phase
DPP-2019 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 18–36 months
Proposed COD: 2021-04-30
MISO-J1437 is a proposed 180 MW wind generation project in Carroll County, Arkansas, within the Midcontinent Independent System Operator (MISO) region. The project consists of a single wind component of 180 MW. The interconnecting utility is Arkansas Electric Cooperative Corporation, and the proposed point of interconnection is the AECC Dry Creek 161kV Switchyard Station. The project has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO interconnection queue on April 29, 2019, and was studied in the DPP-2019 South study cycle. It holds active status in the queue. Its interconnection agreement is dated December 22, 2021, and the IA status is listed as "Construction." The proposed commercial operation date was April 30, 2021, which is earlier than the date of the interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AR
County
Carroll
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ARKANSAS ELECTRIC COOPERATIVE CORPORATION
Entity
MISO
Service Type
NRIS
Point of Interconnection
AECC Dry Creek 161kV Switchyard Station
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WEC.ERG1
- POI Substation
- Oak Creek Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.