Project MISO-J1410 — Project Summary

Queue ID
MISO-J1410
Capacity
300 MW
Technology
Solar
Status
active
Location
Dane, WI
Region
MISO
Developer
—
IA Status
Construction

MISO-J1410

MISO-J1410BetaActiveSolarMISOLBNL + Live

300 MW generation in Dane, WI · In queue since April 2019 · Proposed COD October 2022

BA: MISOISO/RTO: MISONERC: MRORC: MISO

300 MW

Capacity

1

Components

Solar

7y 6m

In Queue

Construction

IA Phase

Signed Mar 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 11m

Total Duration

3y 11m

Schedule

49 months past proposed COD

Study Phase

DPP-2019 East (ATC)

Construction38%
Queue EntryApr 29, 2019

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection AgreementMar 23, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Done; post-GIA Under Construction; GIA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2022-10-30

About

MISO-J1410 is a proposed 300 MW solar generation project located in Dane County, Wisconsin. The project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with American Transmission Co. serving as the interconnecting transmission utility. No developer is identified in the available queue data. The project would connect to the grid at the N. Madison 345 kV Substation and has requested Network Resource Interconnection Service (NRIS).

The project entered the MISO queue on April 29, 2019, and was studied as part of the DPP-2019 East (ATC) study cycle. Its proposed commercial operation date was October 30, 2022. The project's interconnection agreement status is listed as "Construction," with an associated date of March 23, 2023. As of the most recent queue data, the project remains in active status.

Generated from interconnection queue and public data sources

Development Risk

Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD within window)
Cost overrun probability
Schedule slippage vs plan
Project Details

State

WI

County

Dane

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

—

Utility

American Transmission Co.

Entity

MISO

Service Type

NRIS

Point of Interconnection

N. Madison 345 kV Substation

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
Curtailment risk by node
Weather + policy scenarios
Financial Forecast

Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

First-year DSCR
Cost overrun probability
Price + demand scenarios
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
HIGH
POI Substation
Madison

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project MISO-J1410
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.