MISO-J1399
90 MW generation in Ingham, MI · In queue since April 2019 · Proposed COD December 2021
90 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Phase
Signed Aug 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 4m
Total Duration
3y 4m
Schedule
60 months past proposed COD
Study Phase
DPP-2019 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2021-12-01
MISO-J1399 is a proposed 90 MW solar generation project located in Ingham County, Michigan. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Michigan Electric Transmission Company (METC) as the associated transmission owner. The project is proposed to interconnect at the Delhi–Churchill–Tompkins 138 kV transmission line and has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO queue on April 29, 2019, and was studied as part of the DPP-2019 East (ITC) cycle of MISO's Definitive Planning Phase. Its proposed commercial operation date was December 1, 2021. An interconnection agreement was executed on August 17, 2022, later than the originally proposed operation date. As of the most recent data, the project's queue status remains active.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Ingham
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
Delhi - Churchill - Tompkins 138kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1399Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.