MISO-J1392
100 MW generation in Lagrange, IN · In queue since April 2019 · Proposed COD October 2023
100 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Phase
Signed Jun 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 2m
IA → COD
4 months
Total Duration
4y 2m
Schedule
36 months past proposed COD
Study Phase
DPP-2019 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2023-10-30
MISO-J1392 is a proposed 100 MW solar generation project located in Lagrange County, Indiana. The project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO) and would connect to the transmission system of the Northern Indiana Public Service Company. Its designated point of interconnection is the Lagrange 138 kV Substation. No developer or project name has been publicly identified in the queue data.
The project entered the MISO queue on April 29, 2019, and was studied as part of the DPP-2019 Central study cycle. It requested Network Resource Interconnection Service (NRIS). An interconnection agreement was executed on June 15, 2023. The project's proposed commercial operation date was October 30, 2023. As of the latest queue data, its status remains active.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Lagrange
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Lagrange 138 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- LaGrange Park Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.