MISO-J1360
300 MW generation in Piatt, IL · In queue since April 2019 · Proposed COD April 2022
300 MW
Capacity
1
Components
Wind
7y 6m
In Queue
IA Executed
IA Phase
Signed Aug 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 4m
Total Duration
3y 4m
Schedule
55 months past proposed COD
Study Phase
DPP-2019 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 18–36 months
Proposed COD: 2022-04-20
MISO-J1360 is a proposed 300 MW wind generation project in Piatt County, Illinois. It is located within the service territory of Ameren Illinois and would connect to the grid at the Goose Creek 345kV Switchyard. The project consists of a single wind component with a capacity of 300 MW. No developer is identified in the available data.
The project is listed as active in the Midcontinent Independent System Operator (MISO) interconnection queue, which it entered on April 29, 2019. It was studied as part of the DPP-2019 Central cycle and requested Energy Resource Interconnection Service (ERIS). The project has reached the IA Executed stage, with its interconnection agreement dated August 16, 2022. Its proposed commercial operation date was April 20, 2022, which falls before the date the interconnection agreement was executed.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Piatt
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
ERIS
Point of Interconnection
Goose Creek 345kV Switchyard
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Goose Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1360Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.