MISO-J1355
160 MW storage in Laporte, IN · In queue since April 2019 · Proposed COD May 2023
160 MW
Capacity
1
Components
Battery
7y 6m
In Queue
IA Executed
IA Phase
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 1m
Schedule
41 months past proposed COD
Study Phase
DPP-2019 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 6–18 months
Proposed COD: 2023-05-30
MISO-J1355 is a proposed 160 MW battery energy storage project located in LaPorte County, Indiana. The standalone storage facility consists of a single battery component with a capacity of 160 MW. No developer is identified in the available interconnection data. The project would connect to the transmission system of Northern Indiana Public Service Company (NIPSCO) at the Stillwell 138 kV Substation, its designated point of interconnection.
The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, which it entered on April 29, 2019. It was evaluated as part of the DPP-2019 Central study cycle and has requested Network Resource Interconnection Service (NRIS). As of the latest available data, the project holds an active status and has an executed interconnection agreement (IA). Its proposed commercial operation date was May 30, 2023.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Laporte
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Stillwell 138kV Subtation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Stillwell Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1355Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.