MISO-J1320
150 MW generation in Branch, MI · In queue since April 2019 · Proposed COD April 2019
150 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Phase
Signed Apr 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4 years
Total Duration
4 years
Schedule
92 months past proposed COD
Study Phase
DPP-2019 East (ITC)
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2019-04-20
MISO-J1320 is a proposed 150 MW solar generation project located in Branch County, Michigan. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with METC serving as the transmission owner. It is proposed to connect to the grid at the Coldwater - Batavia 138kV Line point of interconnection and has requested Network Resource Interconnection Service (NRIS). No developer is identified in the available queue data.
The project entered the MISO queue on April 29, 2019, and was studied as part of the DPP-2019 East (ITC) study phase. Its listed proposed commercial operation date is April 20, 2019, which precedes the queue entry date as reported in the data. The project remains in active status, and its interconnection agreement (IA) was executed on April 3, 2023.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MI
County
Branch
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
Coldwater - Batavia 138kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.