MISO-J1306
200 MW generation in Perry, IL · In queue since April 2019 · Proposed COD December 2021
200 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Phase
Signed May 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
5y 1m
Total Duration
5y 1m
Schedule
60 months past proposed COD
Study Phase
DPP-2019 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2021-12-01
MISO-J1306 is a proposed 200 MW solar generation project located in Perry County, Illinois. The development project is situated within the service territory of Ameren Illinois and is planned to interconnect to the transmission grid at the Commodore-Jordan 345 kV line. The project consists of a single solar component with a capacity of 200 MW and has requested Network Resource Interconnection Service (NRIS).
The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on April 29, 2019, and was studied as part of the DPP-2019 Central cycle. It remains active in the queue. An interconnection agreement was executed on May 14, 2024. The proposed commercial operation date listed in the queue data is December 1, 2021, which predates the execution of the interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Perry
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
Commodore-Jordan 345kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1306Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.