MISO-J1272
50 MW storage in Vanderburgh, IN · In queue since April 2019 · Proposed COD July 2022
50 MW
Capacity
1
Components
Battery
7y 6m
In Queue
Construction
IA Phase
Signed Sep 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 5m
Total Duration
3y 5m
Schedule
53 months past proposed COD
Study Phase
DPP-2019 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 6–18 months
Proposed COD: 2022-07-01
MISO-J1272 is a proposed 50 MW battery energy storage development project located in Vanderburgh County, Indiana. The standalone storage project would interconnect at the Angel Mound 138kV Substation, within the service territory of Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc. No developer is identified in the available queue data.
The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on April 29, 2019, and was studied in the DPP-2019 Central study cycle. It requested Energy Resource Interconnection Service (ERIS). The proposed commercial operation date was July 1, 2022. The project's interconnection agreement is dated September 2, 2022, and its interconnection agreement status is listed as "Construction." The project remains active in the queue.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Vanderburgh
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc.
Entity
MISO
Service Type
ERIS
Point of Interconnection
Angel Mound 138kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.