Project MISO-J1269 — Project Summary

Queue ID
MISO-J1269
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Warrick, IN
Region
MISO
Developer
—
IA Status
Construction

MISO-J1269

MISO-J1269BetaActiveSolarBatteryMISOLBNL + Live

100 MW hybrid in Warrick, IN · In queue since April 2019 · Proposed COD July 2022

BA: MISOISO/RTO: MISONERC: RFCRC: MISO

100 MW

Capacity

1

Components

Solar

7y 6m

In Queue

Construction

IA Phase

Signed Sep 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

6y 5m

Total Duration

6y 5m

Schedule

53 months past proposed COD

Study Phase

DPP-2019 Central

Construction38%
Queue EntryApr 29, 2019

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection AgreementSep 23, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Done; post-GIA Under Construction; GIA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2022-07-01

About

MISO-J1269 is a proposed hybrid solar and battery storage development project located in Warrick County, Indiana. The project has a total capacity of 100 MW, with the solar component accounting for the full 100 MW. A battery storage component is also included, but its individual capacity is not specified. The interconnecting utility is Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc. The project's point of interconnection is the Elliott 69kV Substation. No developer has been publicly identified in the queue data.

The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on April 29, 2019. It was studied as part of the DPP-2019 Central cycle and requested Energy Resource Interconnection Service (ERIS). It remains in active status. The proposed commercial operation date was July 1, 2022, a date that has since passed. The project's interconnection agreement status is listed as "Construction," with an associated date of September 23, 2025.

Generated from interconnection queue and public data sources

Development Risk

Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD within window)
Cost overrun probability
Schedule slippage vs plan
Project Details

State

IN

County

Warrick

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

—

Utility

Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc.

Entity

MISO

Service Type

ERIS

Point of Interconnection

Elliott 69kV Substation

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
Curtailment risk by node
Weather + policy scenarios
Financial Forecast

Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

First-year DSCR
Cost overrun probability
Price + demand scenarios
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
INDIANA.HUB
Hub Confidence
HIGH
POI Substation
Elliott Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.