MISO-J1268
150 MW generation in Lincoln, MO · In queue since April 2019 · Proposed COD November 2022
150 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Phase
Signed Apr 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
6 years
Total Duration
6 years
Schedule
48 months past proposed COD
Study Phase
DPP-2019 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2022-11-30
MISO-J1268 is a proposed 150 MW solar generation project located in Lincoln County, Missouri. The development project is situated within the service territory of Ameren Missouri and would interconnect to the grid at the Pike - Troy 161kV Line. The project consists of a single solar component with a capacity of 150 MW and has requested Network Resource Interconnection Service (NRIS).
The project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), which it entered on April 29, 2019. It was studied as part of the DPP-2019 Central study phase and remains in active status. An interconnection agreement (IA) for the project was executed on April 23, 2025. The project's proposed commercial operation date was November 30, 2022, a date that preceded the execution of its interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MO
County
Lincoln
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Ameren Missouri
Entity
MISO
Service Type
NRIS
Point of Interconnection
Pike - Troy 161kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1268Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.