MISO-J1219
100 MW generation in Tangipahoa Parish, LA · In queue since April 2019 · Proposed COD October 2022
100 MW
Capacity
1
Components
Solar
7y 6m
In Queue
Construction
IA Phase
Signed Nov 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 7m
IA → COD
11 months
Total Duration
2y 7m
Schedule
49 months past proposed COD
Study Phase
DPP-2019 South
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2022-10-30
MISO-J1219 is a proposed 100 MW solar development project located in Tangipahoa Parish, Louisiana. The project is in the interconnection queue of the Midcontinent Independent System Operator (MISO) and would connect within the service territory of Entergy Louisiana. Its proposed point of interconnection is the Chicken Farm–Amite 115 kV transmission line. The project has requested Network Resource Interconnection Service (NRIS). No project name or developer has been publicly identified in the queue data.
The project entered the MISO queue on April 27, 2019, and was studied as part of the DPP-2019 South study cycle. An interconnection agreement was executed on November 30, 2021, and the agreement status is listed as "Construction." The project's proposed commercial operation date was October 30, 2022. As of the latest queue data, the project remains in active status.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
LA
County
Tangipahoa Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
NRIS
Point of Interconnection
Chicken Farm - Amite 115 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1219Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.