MISO-J1199
20 MW hybrid in Fulton, IL · In queue since April 2019 · Proposed COD June 2021
20 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Phase
COD target: 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 2m
Schedule
65 months past proposed COD
Study Phase
DPP-2019 Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 18–30 months
Proposed COD: 2021-06-15
MISO-J1199 is a proposed hybrid solar and battery storage development project located in Fulton County, Illinois. The project has a total capacity of 20 MW, with the solar component accounting for the full 20 MW listed; no separate capacity figure is specified for the battery storage component. The developer is not identified in the available data. The project is located within the service territory of Ameren Illinois and is proposed to interconnect at the Duck Creek 345kV Substation.
The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on April 25, 2019, and was studied as part of the DPP-2019 Central study cycle. It has requested Network Resource Interconnection Service (NRIS). An interconnection agreement has been executed, and the project remains active in the queue. Its proposed commercial operation date was June 15, 2021.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Fulton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
Duck Creek 345kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1199Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.