50 MW generation in Union, IA · In queue since March 2018 · Proposed COD October 2021
50 MW
Capacity
1
Components
Solar
8y 7m
In Queue
Construction
IA Phase
Signed Feb 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 11m
Total Duration
3y 11m
Schedule
62 months past proposed COD
Study Phase
DPP-2018-APR West
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 12–24 months
Proposed COD: 2021-10-01
MISO-J1132 is a proposed 50 MW solar generation project located in Union County, Iowa. The development project is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with ITC Midwest as the associated transmission utility. The project's proposed point of interconnection is the Creston East 69 kV Substation, and it has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO queue on March 12, 2018, and was studied as part of the DPP-2018-APR West study cycle. Its originally proposed commercial operation date was October 1, 2021. An interconnection agreement was executed on February 7, 2022, and the project's interconnection agreement status is listed as "Construction." As of the latest available data, the project remains active in the queue.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IA
County
Union
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
NRIS
Point of Interconnection
Creston East 69 kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTW.CRSTNSOL
- POI Substation
- Creston East Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1132Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.