MISO-J1069
200 MW generation in Jasper, IN · In queue since March 2018 · Proposed COD September 2022
200 MW
Capacity
1
Components
Wind
8y 7m
In Queue
Construction
IA Phase
Signed Oct 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 7m
IA → COD
11 months
Total Duration
3y 7m
Schedule
51 months past proposed COD
Study Phase
DPP-2018-APR Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Under Construction; GIA
Project under construction
Typical: 18–36 months
Proposed COD: 2022-09-01
MISO-J1069 is a proposed 200 MW wind generation project located in Jasper County, Indiana. The development project consists of a single wind component with a capacity of 200 MW. It is planned to interconnect at the Reynolds 345kV Substation within the service territory of Northern Indiana Public Service Company (NIPSCO). It is registered in the Midcontinent Independent System Operator (MISO) region.
The project entered the MISO interconnection queue on March 12, 2018, and was studied as part of the DPP-2018-APR Central study cycle. It requested Network Resource Interconnection Service (NRIS). An interconnection agreement was executed on October 12, 2021, and the IA status is listed as "Construction." The proposed commercial operation date was September 1, 2022, and the project's queue status remains active.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Jasper
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Reynolds 345kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Reynolds Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1069Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.