MISO-J1025
300 MW generation in Knox, MO · In queue since March 2018 · Proposed COD April 2023
300 MW
Capacity
1
Components
Wind
8y 7m
In Queue
IA Executed
IA Phase
Signed Apr 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 1m
IA → COD
1 year
Total Duration
4y 1m
Schedule
43 months past proposed COD
Study Phase
DPP-2018-APR Central
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Done; post-GIA Not Started; GIA
Project under construction
Typical: 18–36 months
Proposed COD: 2023-04-01
MISO-J1025 is a proposed 300 MW wind generation project located in Knox County, Missouri. The development project consists of a single wind component with a capacity of 300 MW. It is listed in the interconnection queue of the Midcontinent Independent System Operator (MISO), with Ameren Transmission Company of Illinois identified as the associated transmission utility. The project's proposed point of interconnection is the Zachary–Maywood 345 kV Line Tap.
The project entered the MISO queue on March 12, 2018, and was studied as part of the DPP-2018-APR Central study cycle. It has requested Network Resource Interconnection Service (NRIS). An interconnection agreement was executed on April 4, 2022, and the project's queue status remains active. The proposed commercial operation date listed in the queue data is April 1, 2023.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MO
County
Knox
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
Zachary - Maywood 345 kV Line Tap
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project MISO-J1025Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.