Bluejacket Solar (MISO-E0053) — Project Summary

Queue ID
MISO-E0053
Capacity
204.88 MW
Technology
Solar
Status
active
Location
Bureau, IL
Region
MISO
Developer
Hoosier Energy
IA Status
In Progress (unknown study)

Bluejacket Solar

MISO-E0053BetaActiveSolarMISOLBNL

204.88 MW generation in Bureau, IL · In queue since November 2025 · Proposed COD December 2028

BA: PJMISO/RTO: MISONERC: SERCRC: MISO

204.88 MW

Capacity

1

Components

Solar

1 year

In Queue

In Progress (unknown study)

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 1m

In Study38%
Queue EntryNov 6, 2025

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 1, 2028
From queue filing
Developer in saved assessment
Hoosier Energy
From queue filing
Status at research time
Active
Active — queue position secured, interconnection study in progress, no public construction timeline announced
Financing
Not recorded

Milestones in this assessment

IA executedNov 2025Latest in this assessment

Entered MISO queue with interconnection study in progress

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of December 2028. No independent news or press releases found to validate or contradict this target date.

Developer: LBNL lists 'Hoosier Energy' as developer. This appears to be the operating entity name rather than a project-specific LLC. No news coverage found to confirm or provide additional detail on ownership structure.

Status: LBNL status shows 'active' with IA in progress. No news coverage found to indicate construction start, permitting milestones, or project advancement beyond queue filing.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Bluejacket Solar is a proposed 204.88 MW solar generation project in Bureau County, Illinois. The development project is being pursued by Hoosier Energy, which is also listed as the associated utility. The project consists of a single solar component totaling 204.88 MW. It would connect to the grid at the Bureau-Princeton 138kV point of interconnection and has requested Network Resource Interconnection Service (NRIS).

The project is listed as active in the Midcontinent Independent System Operator (MISO) interconnection queue under queue ID MISO-E0053. It entered the queue on November 6, 2025, and has a proposed commercial operation date of December 1, 2028. Its interconnection agreement status is recorded as in progress, though the specific study phase is not identified in the available data.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

IL

County

Bureau

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Hoosier Energy

Utility

Hoosier Energy

Entity

MISO

Service Type

NRIS

Point of Interconnection

Bureau-Princeton 138kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
ILLINOIS.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.