MISO-E0049
798.15 MW generation in Cerro Gordo, IA · In queue since October 2025 · Proposed COD April 2028
798.15 MW
Capacity
1
Components
Gas
1y 1m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-15
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only the LBNL snapshot is available (proposed_cod 2028-04-15); no news or live search findings exist to confirm or contradict it.
Developer: Developer name comes only from the LBNL filing. IPL is an operating utility (Alliant Energy subsidiary) rather than a shell LLC, but no external source corroborates it.
Status: LBNL lists status as active with IA in progress and the project not operational. No newer sources contradict this.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
MISO-E0049 is a proposed natural gas-fired generation project in Cerro Gordo County, Iowa, with a total planned capacity of 798.15 MW. The development project is sponsored by Interstate Power and Light Company (IPL), which is also listed as the associated utility. The project would interconnect to the grid at the Killdeer point of interconnection and has requested Network Resource Interconnection Service (NRIS).
The project entered the Midcontinent Independent System Operator (MISO) interconnection queue on October 15, 2025, and remains active. Its proposed commercial operation date is April 15, 2028. The interconnection agreement is listed as in progress, though the specific study phase is not identified in the available data.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IA
County
Cerro Gordo
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
Interstate Power and Light Company (IPL)
Utility
Interstate Power and Light Company (IPL)
Entity
MISO
Service Type
NRIS
Point of Interconnection
Killdeer
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Killdeer Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.