Madison County Combustion Turbine (MISO-E0046) — Project Summary

Queue ID
MISO-E0046
Capacity
267.75 MW
Technology
Gas
Status
active
Location
Anderson, IN
Region
MISO
Developer
Indiana Municipal Power Agency (IMPA)
IA Status
In Progress (unknown study)

Madison County Combustion Turbine

MISO-E0046BetaActiveGasMISOLBNL

267.75 MW generation in Anderson, IN · In queue since August 2025 · Proposed COD April 2028

BA: MISOISO/RTO: MISONERC: RFCRC: MISO

267.75 MW

Capacity

1

Components

Gas

1y 3m

In Queue

In Progress (unknown study)

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

2y 8m

Study Phase

ERAS Study Cycle 2

In Study38%
Queue EntryAug 6, 2025

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 1, 2028
From queue filing
Developer in saved assessment
Indiana Municipal Power Agency (IMPA)
From queue filing
Status at research time
Active
Active — In Progress interconnection study, no public construction timeline announced
Financing
Not recorded

Milestones in this assessment

COD targetApr 1, 2028Latest in this assessment

LBNL queue target commercial operation date

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with April 2028 target. No independent news or press releases found to validate or contradict this date.

Developer: LBNL lists IMPA as developer, which is a municipal power agency (not a shell LLC). No news coverage found to confirm or provide additional ownership details.

Status: LBNL shows active queue status with interconnection study in progress. No news coverage found to provide ground-truth construction or permitting updates.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Madison County Combustion Turbine is a proposed natural gas-fired generation project in Indiana, with its location listed as Anderson. The development project, sponsored by the Indiana Municipal Power Agency (IMPA), which is also listed as the associated utility, has a total proposed capacity of 267.75 MW, consisting entirely of gas-fired generation. The project would connect to the grid at the Noblesville-Fall Creek 345kV point of interconnection and has requested Network Resource Interconnection Service (NRIS).

The project is in the Midcontinent Independent System Operator (MISO) interconnection queue under queue ID MISO-E0046, with a queue entry date of August 6, 2025. It is being evaluated in ERAS Study Cycle 2, and its interconnection agreement status is listed as in progress, though the specific study stage is not identified. The project's status is active, and its proposed commercial operation date is April 1, 2028.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

IN

County

Anderson

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Indiana Municipal Power Agency (IMPA)

Utility

Indiana Municipal Power Agency (IMPA)

Entity

MISO

Service Type

NRIS

Point of Interconnection

Noblesville-Fall Creek 345kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
INDIANA.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.