Malden BESS
630.42 MW storage in Porter, IN · In queue since August 2025 · Proposed COD May 2027
630.42 MW
Capacity
1
Components
Battery
1y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cdn.misoenergy.org/ERAS%20Interconnection%20Requests718481.pdf?v=20250925100448
- interconnection.fyi/projects/state/IN
- interconnection.fyi/projects/transmission-owner/northern-indiana-public-service
- infrasure.ai/ask/r/malden-bess
Commercial operation date: Only the LBNL snapshot gives a COD (2027-05-01). The live search results, including the MISO ERAS document and aggregator pages, do not state a different date, so there is no newer signal to override it.
Developer: LBNL lists NIPSCO and the aggregator pages repeat that value. The MISO ERAS document ties the project to NIPSCO's load-growth planning, which is consistent with NIPSCO being the sponsor. No shell LLC or ownership change appears.
Status: LBNL shows active and interconnection.fyi (Indiana list) also shows Active. The ERAS document indicates the project is in an expedited interconnection review, and no withdrawal or construction signal was found.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Malden BESS is a proposed battery energy storage development project in Porter County, Indiana, with a total capacity of 630.42 MW. The project is being developed by NIPSCO, which is also the interconnecting utility. It consists of a single battery storage component and is designated as a standalone storage project. The proposed point of interconnection is the Malden 345kV Substation, a new substation, and the project has requested Network Resource Interconnection Service (NRIS).
The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue under queue ID MISO-E0039. It entered the queue on August 13, 2025, and remains in active status. Its interconnection agreement status is reported as in progress, though the specific study phase is not identified. The project has a proposed commercial operation date of May 1, 2027.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Porter
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
NIPSCO
Utility
NIPSCO
Entity
MISO
Service Type
NRIS
Point of Interconnection
Malden 345kV Substation (new)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.