Mitchell BESS (MISO-E0033) — Project Summary

Queue ID
MISO-E0033
Capacity
526.68 MW
Technology
Battery
Status
active
Location
Lake, IN
Region
MISO
Developer
NIPSCO
IA Status
In Progress (unknown study)

Mitchell BESS

MISO-E0033BetaActiveBatteryMISOLBNL

526.68 MW storage in Lake, IN · In queue since August 2025 · Proposed COD August 2028

BA: MISOISO/RTO: MISONERC: RFCRC: MISO

526.68 MW

Capacity

1

Components

Battery

1y 3m

In Queue

In Progress (unknown study)

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3 years

In Study38%
Queue EntryAug 6, 2025

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-01

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Aug 1, 2028
From queue filing
Developer in saved assessment
NIPSCO
From queue filing
Status at research time
Active
Active in the MISO queue (queue date 2025-08-06). The IA is in progress with no study identified, and there is no public evidence of construction or permitting.
Financing
Not recorded
Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only the LBNL snapshot gives a COD (proposed_cod 2028-08-01). None of the search results confirm a date for the Lake County, IN Mitchell BESS. The Texas 'Zeus Mitchell BESS' and the Virginia 'Mitchell Energy Center' results are different projects.

Developer: LBNL lists NIPSCO as the developer. The Energy-Storage.News article on a NIPSCO subsidiary's BESS deal with Amazon is related, but its snippet does not name Mitchell BESS, so it cannot confirm a parent or subsidiary relationship.

Status: LBNL shows the project as active and not operational. No search result contradicts this or adds ground-level detail for the Indiana project.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Mitchell BESS is a proposed battery energy storage development project in Lake County, Indiana, with a total capacity of 526.68 MW. The project is being developed by NIPSCO, which is also the associated utility. The project consists of a single battery storage component and is classified as a storage project. Its point of interconnection is identified as the Mitchell Gen. Station.

The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue under queue ID MISO-E0033. It entered the queue on August 6, 2025, and remains in active status. The project has requested Network Resource Interconnection Service (NRIS) and has a proposed commercial operation date of August 1, 2028. Its interconnection agreement status is listed as in progress, although the specific study phase is not identified in the available data.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

IN

County

Lake

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

NIPSCO

Utility

NIPSCO

Entity

MISO

Service Type

NRIS

Point of Interconnection

Mitchell Gen. Station

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MISO
Trading Hub
INDIANA.HUB
Hub Confidence
HIGH
POI Substation
Mitchell S. Edgerton Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.