MISO-E0030
820 MW generation in Jefferson, TX · In queue since August 2025 · Proposed COD September 2027
820 MW
Capacity
1
Components
Gas
1y 2m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 1m
Study Phase
ERAS Study Cycle 2
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-25
LBNL queue proposed commercial operation date
No description available for this project.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jefferson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
Entergy Texas, Inc.
Utility
Entergy Texas, Inc.
Entity
MISO
Service Type
NRIS
Point of Interconnection
Legend 230kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
OTHERTexasA&M
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.