MISO-E0010
798.15 MW generation in Marshall, IA · In queue since August 2025 · Proposed COD February 2028
798.15 MW
Capacity
1
Components
Gas
1y 3m
In Queue
In Progress (unknown study)
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4 months
IA → COD
2y 2m
Total Duration
4 months
Study Phase
ERAS Study Cycle 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2028-02-06
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only the LBNL snapshot is available, listing a proposed COD of 2028-02-06. No news or live search findings were provided to corroborate or contradict it.
Developer: Only LBNL names the developer, Interstate Power and Light Company, which is an operating utility rather than a shell LLC. No other sources were provided to identify a parent or a change in ownership.
Status: LBNL lists the status as active and the project is not operational. No newer information contradicts this.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
MISO-E0010 is a proposed natural gas-fired generation project located in Marshall County, Iowa, within the Midcontinent Independent System Operator (MISO) region. The development project is being pursued by Interstate Power and Light Company (IPL), which is also the associated utility, and has a total proposed capacity of 798.15 megawatts (MW). The project would connect to the grid at the Twinkle 345 kV Substation and has requested Network Resource Interconnection Service (NRIS).
The project entered the MISO interconnection queue on August 6, 2025, and currently holds an active status. It is being evaluated as part of the Expedited Resource Addition Study (ERAS) Study Cycle 1. Its interconnection agreement is listed as in progress, with an associated date of December 12, 2025. The proposed commercial operation date for the project is February 6, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IA
County
Marshall
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
Interstate Power and Light Company (IPL)
Utility
Interstate Power and Light Company (IPL)
Entity
MISO
Service Type
NRIS
Point of Interconnection
Twinkle 345kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTW.MTOWNCT1
- POI Substation
- Twinkle Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.