Orient Energy Center
265 MW generation in Adair, IA · In queue since August 2025 · Proposed COD September 2027
265 MW
Capacity
1
Components
Gas
1y 3m
In Queue
In Progress (unknown study)
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4 months
IA → COD
1y 9m
Total Duration
4 months
Study Phase
ERAS Study Cycle 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2027-09-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement target completion date per LBNL queue data
Proposed commercial operation date per MISO queue filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2027. No independent news or press releases found to validate or contradict this date.
Developer: LBNL lists MidAmerican Energy Company as developer, which is a major regulated utility (Berkshire Hathaway Energy subsidiary), not a shell LLC. No alternative ownership information found in search results.
Status: LBNL shows active status with interconnection agreement process underway, targeting completion by December 2025. No contradictory information found.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Orient Energy Center is a proposed 265 MW natural gas-fired generation project located in Adair County, Iowa. The development project is being pursued by MidAmerican Energy Company, which is also identified as the interconnecting utility. The project would connect to the transmission system at the Northboro-Orient 345 kV point of interconnection and has requested Network Resource Interconnection Service (NRIS).
The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue under queue ID MISO-E0002, with a queue entry date of August 6, 2025. It is being evaluated as part of MISO's Expedited Resource Addition Study (ERAS) Study Cycle 1, and its queue status is active. The interconnection agreement status is recorded as in progress, with an associated date of December 31, 2025. The proposed commercial operation date for the project is September 1, 2027.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IA
County
Adair
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
MidAmerican Energy Company
Utility
MidAmerican Energy Company
Entity
MISO
Service Type
NRIS
Point of Interconnection
Northboro-Orient 345kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.