Project LGE-KU-LGE-GIS-2022-003 — Project Summary

Queue ID
LGE-KU-LGE-GIS-2022-003
Capacity
660 MW
Technology
Gas
Status
active
Location
Jefferson, KY
Region
Southeast
Developer
—
IA Status
IA Executed

LGE-KU-LGE-GIS-2022-003

LGE-KU-LGE-GIS-2022-003BetaActiveGasLGE-KULBNL

660 MW generation in Jefferson, KY · In queue since June 2022 · Proposed COD April 2027

BA: PJMNERC: SERCRC: MISO

660 MW

Capacity

1

Components

Gas

4y 5m

In Queue

IA Executed

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 10m

Study Phase

TCS 2024

Construction75%
Queue EntryJun 21, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2027-04-01

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Queue ID LGE-KU-LGE-GIS-2022-003 is a proposed 660 MW natural gas-fired generation project located in Jefferson County, Kentucky, in the southeastern United States. The development project is listed in the interconnection queue administered by Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU), with the utility identified as Louisville Gas & Electric and Kentucky Utilities Energy. The project consists of a single gas component rated at 660 MW and is designed to interconnect at the Mill Creek Substation 345 kV bus.

The project entered the LGE-KU interconnection queue on June 21, 2022, and currently holds an active status. It has requested Network Resource Interconnection Service (NRIS) and is associated with the TCS 2024 study phase. An interconnection agreement has been executed for the project, and its proposed commercial operation date is April 1, 2027.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

KY

County

Jefferson

Grid Region

Southeast

Market

—

Developer

—

Utility

Louisville Gas & Electric and Kentucky Utilities Energy

Entity

LGE-KU

Service Type

NRIS

Point of Interconnection

Mill Creek Substation 345 kV bus

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
TVA
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.