LGE-KU-LGE-GIS-2021-020
120 MW hybrid in Mccracken, KY · In queue since June 2021 · Proposed COD December 2026
120 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Phase
COD target: 2026
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-12-31
The proposed project LGE-KU-LGE-GIS-2021-020 is a 120 MW solar and battery hybrid project located in Mccracken County, Kentucky. The developer is Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). The project consists of 120 MW of solar capacity.
The project is currently active in the Louisville Gas & Electric and Kentucky Utilities Energy interconnection queue, with a queue entry date of June 24, 2021, and a proposed commercial operation date of December 31, 2023. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Primary: Grahamville 161 kV bus; Alternate: Grahamville _x0013_ Wickliffe 161 kV line.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KY
County
Mccracken
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
NRIS
Point of Interconnection
Primary: Grahamville 161 kV bus; Alternate: Grahamville – Wickliffe 161 kV line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.