LGE-KU-LGE-GIS-2021-018
110 MW hybrid in Bath, KY · In queue since May 2021 · Proposed COD November 2027
110 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Suspended
IA Phase
COD target: 2027
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-30
The proposed project LGE-KU-LGE-GIS-2021-018 is a 110 MW solar and battery hybrid project located in Bath County, Kentucky. The developer is Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). The project consists of 110 MW of solar capacity.
The project is in the LGE-KU interconnection queue, with an entry date of May 1, 2021, and a proposed commercial operation date of November 30, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Spencer Road to Farmers Tap 138 kV line.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KY
County
Bath
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
NRIS
Point of Interconnection
Spencer Road to Farmers Tap 138 kV line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project LGE-KU-LGE-GIS-2021-018Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.