Project LGE-KU-LGE-GIS-2011-003 — Project Summary

Queue ID
LGE-KU-LGE-GIS-2011-003
Capacity
21 MW
Technology
Hydro
Status
active
Location
Jefferson, KY
Region
Southeast
Developer
IA Status
IA Executed

LGE-KU-LGE-GIS-2011-003

LGE-KU-LGE-GIS-2011-003BetaActiveHydroLGE-KULBNL

21 MW generation in Jefferson, KY · In queue since February 2011 · Proposed COD January 2013

BA: PJMNERC: SERCRC: MISO

21 MW

Capacity

1

Components

Hydro

15y 5m

In Queue

IA Executed

IA Phase

COD target: 2013

Interconnection

Total Duration

1y 11m

Schedule

165 months past proposed COD

Construction75%
Queue EntryFeb 22, 2011

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2013-01-01

About

The proposed LGE-KU-LGE-GIS-2011-003 project is a 21 MW hydroelectric generation facility located in Jefferson County, Kentucky. The project is being developed by Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). It consists of a single 21 MW hydro component.

The project is in the Louisville Gas & Electric and Kentucky Utilities Energy interconnection queue, with an entry date of February 22, 2011. The proposed commercial operation date was January 1, 2013, and the interconnection agreement has been executed. The point of interconnection is the Ohio Falls Uprate.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

KY

County

Jefferson

Grid Region

Southeast

Market

Developer

Utility

Louisville Gas & Electric and Kentucky Utilities Energy

Entity

LGE-KU

Service Type

NRIS

Point of Interconnection

Ohio Falls Uprate

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
TVA
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Project LGE-KU-LGE-GIS-2011-003
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.