LADWP-Q112
1,000 MW storage in San Bernardino, CA · In queue since October 2024 · Proposed COD July 2028
1,000 MW
Capacity
1
Components
Battery
1y 9m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
LADWP-Q112 is a proposed 1000 MW battery storage project located in San Bernardino County, California. The project is being developed by the Los Angeles Department of Water and Power (LADWP). It consists of a single 1000 MW battery component.
The project is currently active in the LADWP interconnection queue as of October 10, 2024, with a proposed commercial operation date of July 1, 2028. The interconnection agreement is currently in progress, with the specific study type unknown. The point of interconnection is the Marketplace-Adelanto 500kV Line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Bernardino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Marketplace-Adelanto 500kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project LADWP-Q112Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.