LADWP-Q108
500 MW storage in San Bernardino, CA · In queue since June 2024 · Proposed COD July 2028
500 MW
Capacity
1
Components
Battery
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
LADWP-Q108 is a proposed 500 MW battery storage project located in San Bernardino County, California. The project is being developed by the Los Angeles Department of Water and Power (LADWP). It is listed in the LADWP interconnection queue as of June 19, 2024, with a proposed commercial operation date of July 1, 2028. The interconnection point of contact is the Victorville 500kV Switching Station. The interconnection agreement status is listed as "In Progress (unknown study)".
The project consists of 500 MW of battery storage capacity. It is currently listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Victorville 500kV Switching Station
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project LADWP-Q108Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.