Project JEA-JEA-Q011 — Project Summary

Queue ID
JEA-JEA-Q011
Capacity
74.9 MW
Technology
Solar+Battery
Status
active
Location
Duval, FL
Region
Southeast
Developer
IA Status
Feasibility Study

JEA-JEA-Q011

JEA-JEA-Q011BetaActiveSolarBatteryJEALBNL

74.9 MW hybrid in Duval, FL · In queue since May 2024 · Proposed COD December 2026

BA: FPLNERC: FRCCRC: FRCC

74.9 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Feasibility Study

IA Phase

COD target: 2026

Interconnection

Total Duration

2y 7m

Feasibility Study13%
Queue EntryMay 9, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

About

The proposed JEA-JEA-Q011 project is a 74.9 MW hybrid Solar+Battery development project located in Duval County, Florida. The project, consisting of 74.9 MW of solar capacity, is in the Jacksonville Electric Authority (JEA) interconnection queue with an entry date of May 9, 2024. The proposed commercial operation date is December 31, 2026.

The project's interconnection status is currently in the Feasibility Study phase. The point of interconnection is the Caldwell substation. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

FL

County

Duval

Grid Region

Southeast

Market

Developer

Utility

Jacksonville Electric Authority

Entity

JEA

Service Type

NRIS

Point of Interconnection

Caldwell

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
FRCC
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.