BD Solar Church Hill
20 MW generation in Androscoggin, ME · In queue since February 2020 · Proposed COD June 2028
20 MW
Capacity
1
Components
Solar
6y 5m
In Queue
IA Executed
IA Phase
Signed Feb 2024
Queue → IA
4 years
IA → COD
4y 4m
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-06-30
The BD Solar Church Hill project is a proposed 20 MW solar generation project located in Androscoggin County, Maine. The project, developed under the ISO-NE queue as queue ID 953, entered the interconnection queue on February 19, 2020. Its proposed commercial operation date is December 31, 2026, and the project has an Interconnection Agreement (IA) executed.
The project is interconnected to the ISO-NE grid at the 101105 Augusta East with New Breaker point of interconnection. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ME
County
Androscoggin
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
ERIS
Point of Interconnection
101105 Augusta East w New Breaker
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.MAINE
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about BD Solar Church HillForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.