Battery Storage
180 MW storage in Worcester, MA · In queue since May 2024 · Proposed COD April 2028
180 MW
Capacity
1
Components
Battery
2y 2m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-27
Project entered ISO-NE queue, interconnection study phase initiated
A proposed 190 MW battery storage project, known as Battery Storage (ISO-NE-1551), is under development in Worcester County, Massachusetts. The project, located within the ISO-NE region, consists entirely of battery storage. It entered the ISO-NE interconnection queue on May 31, 2024, with a proposed commercial operation date of January 31, 2027. The project's interconnection status is currently in the System Impact Study phase.
The Primary Point of Interconnection will be located on the project's property at coordinates 42°21'44.53"N, 72°2'22.57"W, tapping the 115-kV Line A127-4 (Barre-Paxton) approximately 6 km from Barre Substation, which is owned by MA_NGRID.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MA
County
Worcester
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
NRIS
Point of Interconnection
The Point of Interconnection will be located on the IC’s property (Lat, long: 42°21'44.53"N, 72° 2'22.57"W) by tapping the 115-kV Line A127-4 (Barre-Paxton) at approx. 6km from Barre Substation owned by MA_NGRID.
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ISO-NE
- Trading Hub
- .H.INTERNAL_HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LD.BARRE 13.8
- POI Substation
- Barre Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.