Battery Storage
170 MW storage in Berkshire, MA · In queue since May 2024 · Proposed COD December 2029
170 MW
Capacity
1
Components
Battery
2y 2m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2029
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
Entered ISO-NE interconnection queue as project ISO-NE-1546
The Battery Storage project is a proposed 202.07 MW battery storage development in Berkshire County, Massachusetts. The project, located within the ISO-NE region, consists of a single 202.07 MW battery component. It is listed in the ISO-NE interconnection queue as entry number 1546, with a queue entry date of May 30, 2024.
The proposed commercial operation date for the Battery Storage project is June 6, 2030. Its interconnection status is currently in the Feasibility Study phase. The point of interconnection is the MA_WMECO Partridge 115kV substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MA
County
Berkshire
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
NRIS
Point of Interconnection
MA_WMECO Partridge 115kV substation.
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ISO-NE
- Trading Hub
- .H.INTERNAL_HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LD.PARTRIDG23
- POI Substation
- Partridge Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.