Battery Storage (ISO-NE-1320) — Project Summary

Queue ID
ISO-NE-1320
Capacity
203.949997 MW
Technology
Battery
Status
active
Location
Worcester, MA
Region
ISO-NE
Developer
—
IA Status
IA Executed

Battery Storage

ISO-NE-1320BetaActiveBatteryISO-NELBNL + Live

203.95 MW storage in Worcester, MA · In queue since October 2022 · Proposed COD November 2027

BA: ISISO/RTO: ISONENERC: NPCCRC: ISNE

203.95 MW

Capacity

1

Components

Battery

4y 1m

In Queue

IA Executed

IA Phase

Signed Feb 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 4m

IA → COD

2y 9m

Total Duration

2y 4m

Construction75%
Queue EntryOct 7, 2022

Interconnection request submitted to ISO/RTO

TCS Study

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection AgreementFeb 28, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

A

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-11-16

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.

Research COD
Nov 16, 2027
From queue filing
Developer in saved assessment
—
Status at research time
IA Executed
IA Executed — interconnection agreement signed February 2025, project remains in active queue status
Financing
Not recorded

Milestones in this assessment

IA executedFeb 28, 2025Latest in this assessment

Interconnection Agreement executed with ISO-NE

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of November 2027. No independent news or research sources found to validate or contradict this date.

Developer: LBNL filing shows null developer field. No press releases, corporate announcements, or news coverage found identifying the project sponsor or operating company.

Status: LBNL shows IA executed on 2025-02-28, which is recent and represents current legal standing. No contradictory information found in research.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Battery Storage project (ISO-NE-1320) is a proposed 203.95 MW battery storage project located in Worcester County, Massachusetts. The project consists solely of battery storage. It is in the ISO-NE interconnection queue as of October 7, 2022, with a proposed commercial operation date of November 16, 2027.

The interconnection agreement for the project is currently in progress, with the specific study being conducted not specified. The point of interconnection is on the National Grid 115KV Line R144 between Millbury No. 2 and Woonsocket substations, approximately 5.8 circuit miles from Woonsocket substation. The project has appeared in recent news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ISONE queue source as of: Oct 25, 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

MA

County

Worcester

Grid Region

ISO New England

Market

ISO/RTO Member

Developer

—

Utility

—

Entity

ISO-NE

Service Type

NRIS

Point of Interconnection

National Grid 115KV Line R144 between Millbury No. 2 and Woonsocket substations - approximately 5.8 circuit miles from Woonsocket substation.

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ISO-NE
Trading Hub
.H.INTERNAL_HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
LD.WOONSCKT13.8
POI Substation
Woonsocket Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.