Roxbury Solar
1.999 MW generation in Oxford, ME · In queue since October 2021 · Proposed COD December 2026
1.999 MW
Capacity
1
Components
Solar
4y 9m
In Queue
IA Executed
IA Phase
Signed Sep 2023
Queue → IA
1y 11m
IA → COD
3y 3m
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-12-15
The Roxbury Solar project is a proposed 2.0 MW solar generation project located in Oxford County, Maine. The project is listed in the ISO-NE interconnection queue as queue ID ISO-NE-1169. The queue entry date is October 22, 2021, and the proposed commercial operation date is February 7, 2025.
The Roxbury Solar project has an executed Interconnection Agreement (IA). The point of interconnection is the CMP 12.47 kV distribution circuit 447D1 out of the CMP Rumford Substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ME
County
Oxford
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
ERIS
Point of Interconnection
CMP 12.47 kV distribution circuit 447D1 out of CMP Rumford Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.MAINE
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.