Battery Storage
205 MW storage in Washington, RI · In queue since September 2021 · Proposed COD December 2029
205 MW
Capacity
1
Components
Battery
4y 10m
In Queue
IA Executed
IA Phase
Signed Nov 2025
Queue → IA
4y 2m
IA → COD
4y 1m
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2029-12-07
Interconnection Agreement executed (LBNL queue data shows 2025-11-24, likely 2024-11-24)
The Battery Storage project is a proposed 205 MW battery storage development in Washington County, Rhode Island. The project, identified as queue ID ISO-NE-1163, is located within the ISO-NE region. It consists of a single 205 MW battery component.
The project entered the ISO-NE interconnection queue on September 22, 2021, with a proposed commercial operation date of June 1, 2026. As of the latest data, the interconnection agreement has not yet been started. The point of interconnection is RIE L190-2, located 0.615 miles from the Davisville substation and 1.935 miles from the Old Baptist substations.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
RI
County
Washington
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
ERIS
Point of Interconnection
RIE L190-2 (0.615 miles from Davisville and 1.935 miles from Old Baptist substations).
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.RHODEISLAND
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Battery StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.