Battery Storage
508.248 MW storage in Middlesex, MA · In queue since June 2021 · Proposed COD May 2028
508.248 MW
Capacity
1
Components
Battery
5y 5m
In Queue
IA Executed
IA Phase
Signed Apr 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 10m
IA → COD
4y 1m
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
A
Project under construction
Typical: 6–18 months
Proposed COD: 2028-05-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
- lowellsun.com/2026/07/29/500-megawatt-battery-storage-facility-coming-to-tyngsboro/
- news.constructconnect.com/boston-area-battery-storage-project-would-deliver-500mw-and-40m-in-local-revenue
Commercial operation date: Only the LBNL snapshot gives a COD (proposed_cod 2028-05-31). No search result ties a dated in-service target to this queue entry. The Tyngsboro 500 MW coverage is a possible match, but the snippets show no COD.
Developer: The LBNL developer field is null. The Lowell Sun and ConstructConnect snippets describe Rhynland Energy's 500 MW River Mill Storage project in Tyngsboro (Middlesex County), which is a plausible match for this 508 MW entry. Nothing confirms the link, and other Middlesex County battery projects, such as the canceled Tewksbury one, are also candidates, so I did not assign a developer.
Status: LBNL shows status 'active' and ia_status 'IA Executed' (2024-04-04), and no source contradicts this. The Tewksbury cancellation (Hillman Energy) cannot be tied to this queue ID.
About
Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Battery Storage project is a proposed 508.25 MW battery storage development in Middlesex County, Massachusetts. It is located within the ISO-NE region and consists entirely of battery technology. The project entered the ISO-NE interconnection queue as queue ID ISO-NE-1143 on June 15, 2021, with a proposed commercial operation date of May 31, 2028. The interconnection agreement (IA) has been executed.
The project has been the subject of recent news coverage, with six articles focusing on deals and industry developments.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ISONE queue source as of: Oct 25, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MA
County
Middlesex
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
NRIS
Point of Interconnection
Mystic 345 kV between breaker 101, 106 and 107
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ISO-NE
- Trading Hub
- .H.INTERNAL_HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Massachusetts growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.