Nutes Solar
20 MW generation in Strafford, NH · In queue since May 2021 · Proposed COD May 2026
20 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Phase
Signed Jan 2025
Queue → IA
3y 8m
IA → COD
1y 4m
Total Duration
3y 8m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-05-15
The Nutes Solar project is a proposed 20 MW solar generation project located in Strafford County, New Hampshire. The project is listed in the ISO-NE interconnection queue as queue ID ISO-NE-1136, with an entry date of May 20, 2021. The proposed commercial operation date is May 15, 2026, and the interconnection agreement has been executed.
The project, under development in the ISO-NE region, consists of 20 MW of solar photovoltaic generation. The point of interconnection is at 4323'7.50"N, 71 1'23.45"W, Direct Tap, Circuit #3174 34.5 kV.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NH
County
Strafford
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
NRIS
Point of Interconnection
43°23'7.50"N, 71° 1'23.45"W, Direct Tap, Circuit #3174 34.5 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.NEWHAMPSHIRE
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Nutes SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.