Hecate Energy Eastern Ave Energy Center (ISO-NE-1115) — Project Summary

Queue ID
ISO-NE-1115
Capacity
250 MW
Technology
Battery
Status
active
Location
Suffolk, MA
Region
ISO-NE
Developer
—
IA Status
IA Executed

Hecate Energy Eastern Ave Energy Center

ISO-NE-1115BetaActiveBatteryISO-NELBNL + Live

250 MW storage in Suffolk, MA · In queue since April 2021 · Proposed COD November 2026

BA: ISISO/RTO: ISONENERC: NPCCRC: ISNE

250 MW

Capacity

1

Components

Battery

5y 7m

In Queue

IA Executed

IA Phase

Signed Sep 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 5m

IA → COD

3y 2m

Total Duration

2y 5m

Schedule

0 months past proposed COD

Construction75%
Queue EntryApr 8, 2021

Interconnection request submitted to ISO/RTO

TCS Study

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection AgreementSep 5, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

A

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-11-09

News-reported activity
as of 2y 2m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activityConstruction startUniversal Hub · 2024-09-08

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 25, 2026 queue source. See the queue record for reported project facts.

Research COD
Nov 2026
From queue filing
Developer in saved assessment
Hecate Energy
Sources agreed at research time
Status at research time
IA Executed
IA Executed — construction started September 2024, permitting progressing through Haverhill Conservation Committee as of October 2024
Financing
Not recorded

Milestones in this assessment

IA executedSep 5, 2023

Interconnection Agreement executed with ISO-NE

lbnl_queue
construction startSep 2024

Construction activities commenced

universalhub.com
Permit approvedOct 2024

1.2 GWh CATL battery project progressing through Haverhill Conservation Committee permitting

pv-magazine-usa.com
COD targetNov 9, 2026Latest in this assessment

Proposed commercial operation date per ISO-NE queue

lbnl_queue
Research sources and reasoning (2 recorded sources)

medium confidence at research time

  1. pv-magazine-usa.com/2024/10/03/1-2-gwh-catl-battery-progresses-through-permitting-in-massachusetts/
  2. universalhub.com/2024/company-charges-forward-large-scale-power-storage

Commercial operation date: LBNL queue shows proposed COD of 2026-11-09. No contradicting dates found in news sources; construction start reported Sept 2024 makes late 2026 COD plausible.

Developer: News extraction confirms 'Hecate Energy' as applicant, matching the project name. LBNL developer field is null but project name includes 'Hecate Energy', consistent with news sources.

Status: LBNL shows IA executed 2023-09-05. News confirms construction start action in Sept 2024 and active permitting Oct 2024, indicating project advancing post-IA.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 25, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Hecate Energy Eastern Ave Energy Center is a proposed 250 MW battery storage project located in Suffolk County, Massachusetts. The project consists of a single 250 MW battery component.

The project is listed in the ISO-NE interconnection queue as queue ID 1115, with an entry date of April 8, 2021, and a proposed commercial operation date of November 9, 2026. Its interconnection agreement has been executed. The point of interconnection is the Sta 488 Chelsea 115 kV substation. The project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ISONE queue source as of: Oct 25, 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

MA

County

Suffolk

Grid Region

ISO New England

Market

ISO/RTO Member

Developer

—

Utility

—

Entity

ISO-NE

Service Type

NRIS

Point of Interconnection

Sta 488 Chelsea 115 kV substation

Data Source

LBNL + Live

ApplicantHecate Energypv magazine USA · 2024-10-03
AgencyHaverhill Conservation Committeepv magazine USA · 2024-10-03
RulingNoticepv magazine USA · 2024-10-03
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ISO-NE
Trading Hub
.H.INTERNAL_HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-03-26