IP-752
4.2 MW generation in Malheur, OR · In queue since August 2024 · Proposed COD March 2025
4.2 MW
Capacity
1
Components
Solar
1y 11m
In Queue
IA Executed
IA Phase
Signed Oct 2025
Queue → IA
1y 2m
Total Duration
1y 2m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-03-01
IP-752 is a proposed solar generation project located in Malheur County, Oregon, with a total capacity of 4.2 MW. The project is listed in the Idaho Power Company interconnection queue (queue entry date: August 22, 2024) and has a proposed commercial operation date of March 1, 2025. The interconnection agreement (IA) for the project has been executed, with an IA date of December 31, 1999.
The proposed project, which is located in the West region, consists solely of solar photovoltaic generation. The point of interconnection (POI) for IP-752 is MRBT41.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Malheur
Grid Region
Mountain West
Market
—
Developer
Fry Foods Inc.
Utility
Idaho Power Company
Entity
IP
Service Type
Other
Point of Interconnection
MRBT41
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project IP-752Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.