IP-662
1,000 MW hybrid in Power, ID · In queue since June 2022 · Proposed COD December 2027
1,000 MW
Capacity
1
Components
Solar
4y 1m
In Queue
IA Executed
IA Phase
Signed Feb 2024
Queue → IA
1y 8m
IA → COD
3y 10m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2027-12-01
The proposed IP-662 project is a 1000 MW solar and battery hybrid development in Power County, Idaho. Developed by Sawtooth DevCo, LLC, the project consists of 1000 MW of solar generation paired with battery storage. Interconnection is with Idaho Power Company via the Borah 345kV Substation.
IP-662 entered the IP interconnection queue on June 16, 2022, with a proposed commercial operation date of December 31, 2025. The project's interconnection agreement was executed on February 1, 2024, and its current status is listed as suspended.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Power
Grid Region
Mountain West
Market
—
Developer
Sawtooth DevCo, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
ERIS
Point of Interconnection
Borah 345kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.