IP-635
1,000 MW hybrid in Gooding, ID · In queue since February 2022 · Proposed COD December 2029
1,000 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Phase
Signed Jun 2023
Queue → IA
1y 4m
IA → COD
6y 6m
Total Duration
1y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2029-12-31
IP-635 is a proposed 1000 MW hybrid solar and battery project located in Gooding County, Idaho. The development project, which also lists wind as a technology detail, is being developed by Taurus Wind LLC and is interconnected with Idaho Power Company. The point of interconnection is the Midpoint 500kV Substation.
The project entered the IP (Idaho Power) interconnection queue on February 7, 2022, with a proposed commercial operation date of December 1, 2026. The interconnection agreement for IP-635 was executed on June 13, 2023, and the project's current status is listed as suspended. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Gooding
Grid Region
Mountain West
Market
—
Developer
Taurus Wind LLC
Utility
Idaho Power Company
Entity
IP
Service Type
NRIS
Point of Interconnection
Midpoint 500kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.