IID-GI-2023-168
387 MW storage in Imperial, CA · In queue since April 2023 · Proposed COD April 2025
387 MW
Capacity
1
Components
Battery
3y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2025
Total Duration
2 years
Schedule
15 months past proposed COD
Study Phase
D
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-01
IID-GI-2023-168 is a proposed energy storage project located in Imperial County, California, within the Imperial Irrigation District (IID) service area. The development project, consisting of 387 MW of battery capacity, entered the IID interconnection queue on April 4, 2023. Its proposed commercial operation date is April 1, 2025.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the 230kV ECSS substation. The project is listed in the West region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
230kV ECSS
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project IID-GI-2023-168Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.