IID-GI-2021-149
175 MW hybrid in Imperial, CA · In queue since November 2021 · Proposed COD April 2024
175 MW
Capacity
1
Components
Solar
4y 8m
In Queue
System Impact Study
IA Phase
COD target: 2024
Total Duration
2y 5m
Schedule
28 months past proposed COD
Study Phase
A
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-01
The proposed IID-GI-2021-149 project is a 175 MW hybrid solar and battery energy storage development in Imperial County, California. The project, located in the western region of the US, is being proposed within the Imperial Irrigation District (IID) interconnection queue. The project entered the queue on November 17, 2021, and is currently undergoing a System Impact Study. The proposed commercial operation date is April 1, 2024.
The hybrid project consists of 175 MW of solar generation capacity. The interconnection point of contact is the 230kV KN line. The project is listed as active within the IID interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Imperial
Grid Region
Mountain West
Market
—
Developer
—
Utility
Imperial Irrigation District
Entity
IID
Service Type
—
Point of Interconnection
230kV KN line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project IID-GI-2021-149Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.