Washington County Solar (GTC-GI-197) — Project Summary

Queue ID
GTC-GI-197
Capacity
203 MW
Technology
Solar+Battery
Status
active
Location
Washington, GA
Region
Southeast
Developer
IA Status
System Impact Study

Washington County Solar

GTC-GI-197BetaActiveSolarBatteryGTCLBNL

203 MW hybrid in Washington, GA · In queue since October 2024 · Proposed COD April 2027

BA: SOCONERC: SERCRC: SOCO

203 MW

Capacity

1

Components

Solar

1y 9m

In Queue

System Impact Study

IA Phase

COD target: 2027

Interconnection

Total Duration

2y 6m

Impact Study25%
Queue EntryOct 1, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-01

Cross-source intelligence
Beta
Low confidence·0 sources·as of 2026-06-01
Expected COD
2027-04-01
From queue filing
Developer
Status
Active
Active — System Impact Study phase in Georgia Transmission Corporation queue, no public construction timeline announced
Financing
Unannounced
Key milestones
IA executedOct 2024Most recent

Entered GTC queue for System Impact Study

About

Washington County Solar is a proposed 200 MW hybrid solar and battery energy storage project located in Washington County, Georgia. The project, developed by an unknown entity, consists of 200 MW of solar generation. It is interconnected to the Georgia Transmission Corporation (GTC) via the Tiger Creek 230kV Substation.

The project is listed in the GTC interconnection queue as entry GTC-GI-197, with a queue entry date of October 1, 2024. Its proposed commercial operation date is April 1, 2047, and its interconnection status is currently in the System Impact Study phase. The Washington County Solar project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

GA

County

Washington

Grid Region

Southeast

Market

Developer

Utility

Georgia Transmission

Entity

GTC

Service Type

Point of Interconnection

Tiger Creek 230 kV Substation

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Washington County Solar
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.