SR Grady_SR Whigham
150 MW generation in Grady, GA · In queue since August 2024 · Proposed COD December 2028
150 MW
Capacity
1
Components
Solar
1y 9m
In Queue
Construction
IA Phase
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-15
The SR Grady project is a proposed 150 MW solar generation project located in Grady County, Georgia. Interconnection is requested through the Georgia Transmission (GTC) queue, identified as GTC-GI-196, with a queue entry date of August 31, 2024. The proposed commercial operation date is December 15, 2028. The project's interconnection status is currently in the System Impact Study phase.
The point of interconnection (POI) is the South Bainbridge _x0013_ Thomasville 230 kV TL. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Grady
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
South Bainbridge – Thomasville 230 kV TL
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about SR Grady_SR WhighamForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.